ARTICLE | January 30, 2024
Authored by RSM US LLP
Executive summary
Transitional rules released for applicable entities making an elective payment election under section 6417
The Department of Treasury (Treasury) and the IRS have released Notice 2024-9 (Notice). The Notice provides transitional rules for Applicable Entities making an elective payment election under section 6417 to claim the statutory exceptions to phaseouts for clean energy credits in the event domestic content requirements are not met. The transitional rules apply to projects where construction begins before Jan. 1, 2025. Treasury and the IRS have requested comments on future regulations that would apply to projects where construction begins on or after Jan. 1, 2025. “Applicable Entities” are generally tax-exempt organizations, state and local governments, Indian tribal governments, Alaska Native Corporations, the Tennessee Valley Authority or rural electric cooperatives. See IR-2023-252.
IRS issues guidance on statutory exceptions to domestic content requirements
The Inflation Reduction of Act of 2022 (IRA) amended the production tax credit under section 45, along with the investment tax credit under section 48, requiring, in part, that taxpayers must satisfy domestic content requirements to receive bonus credit amounts with respect to qualified facilities and energy projects placed in service after Dec. 31, 2022. The IRA also added the new clean energy production credit under section 45Y and new the clean electricity investment credit under section 48E, which provide similar domestic content requirements for bonus credit amounts. On May 12, 2023, Treasury and IRS released Notice 2023-38 to assist taxpayers in determining which energy projects and facilities qualify for the domestic content bonus tax credit. New Treasury guidance on IRA domestic content rules (rsmus.com).
For Applicable Entities making an election under section 6417, the amount of a credit under sections 45, 48, 45Y and 48E will be replaced by the value of the credit multiplied by the applicable percentage. See RSM’s prior alert on the direct pay election under section 6417 IRS and Treasury release guidance on the monetizing energy credits (rsmus.com).
The applicable percentage is 100%, thus preserving the full credit, if the qualified facility of an Applicable Entity meets one of these two requirements:
- Satisfies the domestic content requirements as set forth in Notice 2023-38, or
- Has a maximum net output of less than 1 megawatt.
If the qualified facility of the Applicable Entity does not meet one of these two requirements the applicable percentage may be reduced to 90% unless one of the following applies:
- Construction of the facility began before Jan. 1, 2024
- If construction begins in calendar year 2024 or later:
- The inclusion of steel, iron or manufactured products which are produced in the United States increases the overall cost of construction of qualified facilities by more than 25% (Increased Cost Exception); or
- Relevant steel, iron or manufactured products are not produced in the United States in sufficient and reasonably available quantities or a satisfactory quality (Non-Availability Exception).
The Increased Cost Exception and the Non-Availability Exception are only available to Applicable Entities.
Notice 2024-9
Treasury and IRS released Notice 2024-9, which announced transitional rules for Appliable Entities claiming the Increased Cost Exception and/or the Non-Availability Exception. The transitional rules apply to an energy property or qualified facility if construction begins before Jan. 1, 2025. Under the Notice, an Applicable Entity will need to attest, under penalties of perjury, that it has reviewed the requirements for the Increased Cost Exception and the Non-Availability Exception and has made a good faith determination that the qualified facility, energy project or qualified investment with respect to a qualified facility or energy storage technology, qualifies for either or both, exceptions.
Treasury and the IRS have also requested comments regarding the Increased Cost Exception and the Non-Availability Exception for projects that begin construction on or after Jan. 1, 2025. These comments will help develop future proposed regulations for projects that start construction on or after Jan. 1, 2025. Comments must be submitted by Feb. 26, 2024.
Washington National Tax takeaways
Applicable Entities evaluating energy credit projects should be mindful of these transitional rules. Without proper documentation supporting start of construction, the Increased Cost Exception and/or the Non-Availability Exception, the credit could be reduced. The attestation described in Notice 2024-9 must be signed by a person with legal authority to bind the Applicable Entity and must be attached to an applicable form required to be filed as part of the elective payment election. Given that elective payment elections under section 6417 are expected to be closely reviewed by the IRS, as they provide a payment directly to the Applicable Entity, careful review and documentation of the Increased Cost Exception and the Non-Availability Exception should be completed for projects where construction begins in 2024 or later. Taxpayers interested in submitting comments for projects commencing construction on or after Jan. 1, 2025 should do so as soon as possible.
This article was written by Sara Hutton, Eugene Boakye and originally appeared on 2024-01-30. Reprinted with permission from RSM US LLP.
© 2024 RSM US LLP. All rights reserved. https://rsmus.com/insights/tax-alerts/2024/irs-issues-guidance-statutory-exceptions-domestic-content-requirements.html
RSM US LLP is a limited liability partnership and the U.S. member firm of RSM International, a global network of independent assurance, tax and consulting firms. The member firms of RSM International collaborate to provide services to global clients, but are separate and distinct legal entities that cannot obligate each other. Each member firm is responsible only for its own acts and omissions, and not those of any other party. Visit rsmus.com/about for more information regarding RSM US LLP and RSM International.
The information contained herein is general in nature and based on authorities that are subject to change. RSM US LLP guarantees neither the accuracy nor completeness of any information and is not responsible for any errors or omissions, or for results obtained by others as a result of reliance upon such information. RSM US LLP assumes no obligation to inform the reader of any changes in tax laws or other factors that could affect information contained herein. This publication does not, and is not intended to, provide legal, tax or accounting advice, and readers should consult their tax advisors concerning the application of tax laws to their particular situations. This analysis is not tax advice and is not intended or written to be used, and cannot be used, for purposes of avoiding tax penalties that may be imposed on any taxpayer.
The FMF&E team is eager to learn about you and your business. We are a Central New York based certified public accounting firm serving nationwide clients since 1980. Our experienced and dedicated team provides audit, accounting, tax and consulting services to businesses throughout the United States. Our clients include many energy companies, financial institutions, construction and real estate developers, manufacturers, professional services, and wholesalers and distributors.
FMF&E is a team of over 85 highly skilled and motivated professionals. Our team members possess additional highly valued industry certifications such as Certified Valuation Analyst, Certified Fraud Examiner, Certified Credit Union Internal Auditor, NAFCU Certified Compliance Officer, and more. Our growth has come from applying a strong results-oriented approach to servicing our clients.
For more information on how FMF&E can assist you, please email info@fmfecpa.com.